A rapid-response underground installation restored power to a multi-unit building after service failure, requiring coordinated planning, trenching through adjacent property, and utility integration.
- Assessed service failure and coordinated response with property owner and utility provider
- Developed plan to reroute service through neighboring property
- Performed trench excavation and installed new underground conduit and service conductors
- Installed 400-amp single-phase service infrastructure
- Completed site restoration following installation
- Approximately 130 linear feet of trench excavation for underground service restoration.
- Rapid-response underground service restoration for a multi-unit building following electrical failure.
- Final site restoration including backfill, grading, seeding, and straw.